af nexusadvokater | aug 27, 2021 | Ikke kategoriseret
Brief description of the Danish regulations on liquidated damages The General Conditions for Turnkey Contracts (“Almindelige Betingelser”), which is an agreed document normally used in the building and engineering industry, establish a standard for the employer to...
af nexusadvokater | aug 27, 2021 | Ikke kategoriseret
13.1. The legal literature Erik Hørlyck states in ”Entreprise – AB 18”, version 7, page 163, as a comment to the decision to depreciate that the wording of the decision implies ”that concrete notifications of defects must be submitted. It is not sufficient to prevent...
af nexusadvokater | aug 27, 2021 | Ikke kategoriseret
As an introduction to the subject it can be noted, that according to Hørlyck, the current understanding is that a concurrent delay entitles both the Employer and the Contractor to EoT, as both parties are culpable for a delay. However due to the delay being...
af nexusadvokater | aug 27, 2021 | Ikke kategoriseret
There is no specific described methodology for claim related to acceleration costs, but the following methodology is what suggested based on case law: Short introduction to the claim Explanation of the requirements to get the claim awarded Facts and description of the...
af nexusadvokater | aug 27, 2021 | Ikke kategoriseret
10.1. Disruption claims If the completion of the works becomes disrupted and thus delayed due to e.g. ambiguities in the project, lack of access to the works or unforeseen conditions not caused by the contractor’s circumstances, the contractor may require the...