af nexusadvokater | aug 27, 2021 | Ikke kategoriseret
Based on the currently sparse, legal literature and arbitration practice regarding concurrent delays (parallel delays), the current understanding implies that a concurrent delay entitles the employer as well as the contractor to an extension of time as both parties...
af nexusadvokater | aug 27, 2021 | Ikke kategoriseret
28.1. TBB 2018.649 28.1.1. Summary Introduction The case was about a non-profit housing society for which 40 attic flats were to be built in an existing housing block. Following the completion of a call for tenders, the employer and the contractor concluded a main...
af nexusadvokater | aug 27, 2021 | Ikke kategoriseret
27.1. TBB 2016.696 – Parallel delays – when time is not money 27.1.1. Danish law Parallel delays have only claimed little attention in Danish, legal literature. Thus, common presentations on construction law do not mention parallel delays which is in sharp contrast...
af nexusadvokater | aug 27, 2021 | Ikke kategoriseret
If it can be proven that a delay is caused by the employer, the contractor is generally entitled to an extension of time and financial compensation according to section 27, subs. 1, no. 1 of AB 92. The contractor’s task is to meet the burden of proof that the delay...
af nexusadvokater | aug 27, 2021 | Ikke kategoriseret
Overview Legal literature and arbitration practice regarding concurrent delays (parallel delays) establish that a concurrent delay entitles the employer as well as the contractor to an extension of time while precluding the parties’ potential entitlement to delay...
af nexusadvokater | aug 27, 2021 | Ikke kategoriseret
As mentioned above, a single deviation from agreed formal requirements can lead to the contractor being able to receive payment for documented extra work. In the following, it will be reviewed what the contractor must otherwise prove in order to obtain payment for...